Summer Refurbishment 2018

During the summer holidays 2018 there will be extensive renovation works taking place internally and externally. We have endeavoured to keep customer disruption to a minimum, but inevitably there are some access restrictions and some facility closures.

As the works progress, we will update the information below as to when the affected facilities will re-open and access to facilities will return to normal


Renovation Schedule


Week 2 Update

2/8/2018

Progress on the refurbishment is currently slightly ahead of schedule and we're expecting to get certain facilities back sooner that orinigally anticipated. We will inform customers on the re-opening dates in due course.

*Total Closure

As there will be no power to any facilities, the centre will be closed on 23rd, 24th, 25th, 26th & 27th August.


By Facility


3G Pitch 

LED lighting upgrade - due to be completed Friday 20th July

Open as normal

*Centre Closed 23rd, 24th, 25th, 26th & 27th August.

Sports Hall

Open as normal

W/C 30/7 for 3-4 weeks, no reception access to hall - access via fire exit.

*Centre Closed 23rd, 24th, 25th, 26th & 27th August.

Squash Courts

No access - facilities closed 23rd July for 3-4 weeks.

*Centre Closed 23rd, 24th, 25th, 26th & 27th August.

Gymnasium

Open as normal

W/C 23/7 for 3-4 weeks, no first floor access to gymnasium - access via the fire exit at the rear.

*Centre Closed 23rd, 24th, 25th, 26th & 27th August.

Tennis Courts

Out of use throughout the holidays due to compound areas and construction of our brand new MUGA facilities.

*Centre Closed 23rd, 24th, 25th, 26th & 27th August.

Changing Rooms/Showers

W/C 23/7 for 3 weeks, no access to internal changing facilities / showers.

Temporary changing facility and customer toilets located on the tennis courts. Note - there is no male/female division & there are no shower facilities.

*Centre Closed 23rd, 24th, 25th, 26th & 27th August.

Reception

Our main recepetion area will be inaccessible from 30th July for approx 3 weeks. A temporary customer reception will be located in a portacabin on the tennis courts. 

*Centre Closed 23rd, 24th, 25th, 26th & 27th August.


Should you have any questions or queries throughout these works. Please contact the management.

We apologise for the inconvenience during these works, but look forward to welcoming you back to our 'new look' facilities at the end of August. 